Stover School
5D GROUP were commissioned to install a 480kW Biomass installation to take the place of ageing oil and gas boilers and a number of electrical heaters in classrooms.
The boilers were positioned in a converted barn which became the Energy Centre for the site. A 680m District Heating system was designed and installed to take the heat from the plant to the various buildings and classrooms around the site. A Building Management System was incorporated in the design.
The system has been accepted by Ofgem under the RHI scheme and is expected to pay back the investment within a 7 year timescale.